Transport Canada has signed off on the Trail Regional Airport’s Corrective Action Plan.
This following the federal department’s audit of the facility that had four findings – one of which was major.
Airport Manager Don Goulard then had 30 days to submit the plan.
The audit revealed that about $50,000 of work needs to be done to the facility.
- Advertisement -
The City plans to ask for compensation from the RDKB – who they just bought the airport from.
Goulard says it will take about a year to complete the corrective action plan.