HomeNewsKootenay NewsRDCK looks to award Universal Metering contract for Balfour Water System upgrades

RDCK looks to award Universal Metering contract for Balfour Water System upgrades

Upgrades continue for the Balfour water system. The Regional District of Central Kootenay was accepting applications for the Universal Metering portion of the almost $3-million project.  Area E Director Ramona Faust says a recommendation was made to award the contract to Corix Water Products Limited, but it’s not set in stone yet.

She says they need to start the work soon.

The RDCK originally estimated $475,000 for the metering work, but the proposal closest to their budget came in at over $529,000. There is a contingency fund that will cover the difference.

Faust says there’s a lot work happening on the project right now.

The RDCK did award the contract for the Balfour Reservoir Watermain Connection to Kaslo Industrial for a maximum of $158,445.